B Com Exam  >  B Com Questions  >  The standard cost of a chemical mix is as und... Start Learning for Free
The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.?
Most Upvoted Answer
The standard cost of a chemical mix is as under : 4 tons of material A...
Material Variance Calculation

The material variance is the difference between the standard cost of materials and the actual cost of materials used in the production process. The formula for material variance is:

Material Variance = (Standard Cost – Actual Cost) x Actual Quantity

Using the information given in the problem, we can calculate the material variance as follows:

Standard Cost of Materials = (4 x ` 16) + (8 x ` 18) = ` 160

Actual Cost of Materials = (6 x ` 9) + (7 x ` 15) = ` 123

Actual Quantity = 10 tons

Material Variance = (` 160 – ` 123) x 10 = ` 370

Therefore, the material variance is ` 370.

Explanation of Material Variance

Material variance is a measure of the difference between the standard cost of materials and the actual cost of materials used in the production process. It is used to measure the efficiency of the production process and to identify any variances that need to be addressed.

Material variance is calculated by comparing the actual cost of materials used with the standard cost of materials that should have been used based on the production plan. The variance can be positive or negative, indicating whether the actual cost of materials was higher or lower than expected.

There are two types of material variances:

1. Price Variance – This variance is caused by the difference between the actual price paid for materials and the standard price that was expected.

2. Usage Variance – This variance is caused by the difference between the actual quantity of materials used and the standard quantity that was expected.

In the problem given, the material variance is calculated based on the actual cost of materials used and the standard cost of materials that were expected. The variance is positive, indicating that the actual cost of materials was higher than expected.

Material variance is an important tool for cost control and management. By identifying and analyzing variances, managers can take corrective action to improve efficiency, reduce costs, and increase profitability.
Explore Courses for B Com exam
The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.?
Question Description
The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.? for B Com 2024 is part of B Com preparation. The Question and answers have been prepared according to the B Com exam syllabus. Information about The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.? covers all topics & solutions for B Com 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.?.
Solutions for The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.? in English & in Hindi are available as part of our courses for B Com. Download more important topics, notes, lectures and mock test series for B Com Exam by signing up for free.
Here you can find the meaning of The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.? defined & explained in the simplest way possible. Besides giving the explanation of The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.?, a detailed solution for The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.? has been provided alongside types of The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.? theory, EduRev gives you an ample number of questions to practice The standard cost of a chemical mix is as under : 4 tons of material A @ ` 16 per ton 8 tons of material B @ ` 18 per ton Standard yield is 80% of input. The actual cost for the period is as under : 6 tons of material A @ ` 9 per ton 7 tons of material B @ ` 15 per ton Actual yield is 10 tons. Compute Material Variance.? tests, examples and also practice B Com tests.
Explore Courses for B Com exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev